Works have completed on Phase 1 following Practical completion of Consort House, which was a conversion from office to 30 nr. apartments which included forming a penthouse at roof level.

Phase 2 is the conversion of Royal and Regent House, converting from offices to form 70 new apartments over two storeys. Works, which are due to complete 20th December 2019 are progressing well with the majority of the rooms to ground and first floor boarded and closed. Main Contractor is focusing labour on the second floor to catch up. Challenges on this project have involved new flat roof installations throughout both buildings, with existing pitched tiled structures being stripped, felted and battened and relaying of existing tiles.